Maersk -Tyra Decommissioning to Start Next Year

January 2, 2017

Maersk Oil has on 30th December issued a notification to the Danish gas market announcing that an economically viable solution for full recovery of the remaining resources in the Tyra field has not yet been identified, and that production from the Tyra field is consequently expected to cease 1 October 2018. Under EU regulatory requirements, a decision impacting production must be notified to the market in a timely manner.

“Tyra has since 1984 been the main hub for gas production and processing in the Danish North Sea. The Tyra facilities are approaching the end of their operational life, and together with our partners in DUC we have assessed solutions for safe decommissioning and possible rebuilding of the Tyra facilities,” says Martin Rune Pedersen, Chief Operating Officer, Maersk Oil.

Despite more than DKK 1 billion spend on reinforcing the Tyra structures over the past 15 years, the facilities cannot safely continue production due to new knowledge on storm wave impact, combined with subsidence of the underground chalk reservoir which reduces the gap between the platforms and the sea.

“We have not yet found an economically viable solution for full recovery of the remaining resources in the Tyra field, and safe decommissioning of Tyra will therefore be commenced with the perspective of ceasing production on 1 October 2018. In January 2017 we will have to reallocate resources from Tyra rebuild planning to engineering work for a detailed plan to discontinue the Tyra field as the Danish hub for gas processing,” says Martin Rune Pedersen, Chief Operating Officer, Maersk Oil.

The remaining potential of the Danish North Sea is widely recognised. The dialogue with Danish authorities will be continued in an effort to identify the terms that will allow future investments, including investments in rebuilding Tyra, to secure long-term activities and jobs in the Danish North Sea.
 