Sunday, December 22, 2024

TenneT, Vattenfall Pact on Hollandse Kust Zuid

January 15, 2019

European transmission system operator TenneT Holding and offshore and wind farm developer Vattenfall  have signed agreements for the offshore grid connection for the Hollandse Kust Zuid I and II wind farms.

The agreements concern the realisation of the connection and the transmission of electricity between the 700 MW wind farm of Vattenfall and the TenneT Hollandse Kust Zuid Alpha offshore platform, the grid operator said.

Vattenfall won this first subsidy free public tender issued by the Dutch government in March 2018.

Marco Kuijpers, Senior Manager Offshore Nederland at TenneT: "This agreement is another fantastic step towards making the Dutch electricity system sustainable. The offshore grid is now really taking shape, first with 1,400 MW in the Borssele wind area, followed by Hollandse Kust Zuid and finally Hollandse Kust Noord in 2023. In the meantime, we’re preparing for the next North Sea projects in consultation with the Ministry of Economic Affairs & Climate."

"This is a big milestone for the project and we’re glad that it is advancing well," says Gunnar Groebler, Head of BU Wind and member of the EGM of Vattenfall. "Contracts are signed well ahead of the deadline in March this year. We are looking forward to continue our cooperation with TenneT and materialize this project as a big contribution to the Dutch energy transition."

Hollandse Kust Zuid offshore grid comprises two transformer platforms at sea, each with a 700 megawatt capacity, two 220 kV alternating current cables per platform, a yet-to-be-constructed onshore substation and an expansion of the existing ‘Maasvlakte’ onshore high voltage substation where offshore wind power is connected to TenneT’s Randstad 380 kV Zuidring.

The wind power will be supplied to electricity consumers across the country via the national high voltage grid.

TenneT has been officially designated by the Dutch government as offshore grid operator. TenneT is realising grid connections at sea with a total capacity of at least 3,500 MW, in accordance with a standardised concept of 700 MW per grid connection. The two connections from the Hollandse Kust Zuid offshore grid, which have a joint capacity of 1,400 MW, will become operational a year apart, in 2021 and 2022, in accordance with the Energy Agreement.

Related News