Johan Sverdrup Development Enters Phase 2
“We must take a generational perspective on the Johan Sverdrup development. Working closely with partners and government authorities we now have a plan for Phase 2 that maximizes value for society, industry and the licensees”, says Statoil (STO)’s project director for Johan Sverdrup, Kjetel Digre.
“The Johan Sverdrup suppliers have demonstrated a willingness and capabilities to develop good solutions in a partnership with us. The contributions have been key to the improvements we have achieved so far. We are pleased to see that this trend is being progressed in the awarded FEED contracts. And we see that Norwegian suppliers are competitive in an international market,” says Digre.
“The quality of phase 1 and the improvement work we have performed with our partners and suppliers for phase 2 has enhanced profitability. The break-even price for the full-field development is now less than USD 25 per barrel and with an ambition of a world class recovery rate of 70 %,” says Digre.
The following FEED contracts will be awarded in connection with the decision to proceed with the development that has now been made:
- Processing platform, Aker Solutions
- Jacket, Kværner
- Power supply from shore, Siemens
28 new wells are planned to be drilled in connection with the Phase 2 development.
The Phase 2 concept also includes the establishment of an area-wide solution for power from shore for the Utsira High by 2022.
Maturing and planning Phase 2 parallel with the development of Phase 1 will ensure a consistent full-field solution and cost-efficient hook-up when Phase 1 is on stream. With a field life estimated at 50 years, Johan Sverdrup will generate great value for society and the partners.