USDoE: LNG Reviews must await EIA's
The U.S. Department of Energy announced on Tuesday that it will not be able to finish reviews of two projects for liquefied gas in Louisiana until a regulatory agency independent of the Department has completed its environmental assessments.The DOE stated that it must wait until the Federal Energy Regulatory Commission (FERC) has completed its work to review export applications to countries where the U.S. doesn't have free-trade agreements.
NextDecade, Shell Seal Rio Grande LNG Deal
The liquefied natural gas arm of oil giant Shell has become the first customer at U.S. company NextDecade Corp 's proposed $15 billion Rio Grande LNG export terminal at the Port of Brownsville.NextDecade signed a 20-year binding sales and purchase agreement (SPA) with Royal Dutch Shell for the supply of two million tonnes per annum of LNG.Pursuant to the SPA, Shell will purchase LNG on a free-on-board basis starting from the commercial operation date of Rio Grande LNG…
NextDecade in Rio Grande LNG Site Lease Deal
US LNG export project developer NextDecade Corporation signed a lease agreement with the Brownsville Navigation District (BND) for its Rio Grande LNG project.The proposed $15 billion Rio Grande LNG export terminal and pipeline at the Port of Brownsville, Texas, was considered and approved during a meeting of the BND Board of Commissioners.The lease agreement, which covers an approximately 984-acre parcel of land in Cameron County…
Dallas Company Secures Permits to Expand Crude Export Hub at Texas Port
Jupiter MLP LLC, a Dallas-based logistics company, has secured permits to expand a crude export dock at the Port of Brownsville in Texas, the latest in a series of moves made by U.S. companies to tap into booming overseas shipments.The expanded dock space will be able to accommodate Suezmax-size vessels, the company said in a statement Thursday.Privately-held Jupiter has also begun the permitting process to build an offshore…
Texas LNG Continues Progress in Regulatory Process
Texas LNG Brownsville LLC announced that on May 14, 2015, Resource Reports #1 and #10 were submitted to the Federal Energy Regulatory Commission (FERC) in accordance with the FERC NEPA Pre-fling process schedule for the proposed liquefied natural gas (LNG) export facility in Brownsville, Texas. Resource Report #1 – General Project Description - provides a detailed overview of Project facilities including plot plans, schedules, and required permits.
Braemar Named Engineers for Brownsville LNG Project
Braemar Engineering, the marine and LNG technical consultancy arm of the Braemar Shipping Services PLC group, has been appointed as Owner’s Engineers by Texas LNG Brownsville LLC (Texas LNG) for the proposed Brownsville LNG project. The project will be constructed in a deepwater frontage site along the Port of Brownsville shipping channel, South Texas, and is anticipated to export more than 2 million metric tons per annum (MTPA) of LNG, with the first shipments planned for export in 2019.
Texas LNG Gets Approval To Export LNG To FTA countries
Texas LNG LLC today announced that it has received authorization from the U.S. Department of Energy (DOE) to export domestically produced LNG to all existing, and any future, countries that have, or enter into, an FTA with the Government of the United States. DOE approval of FTA exports is an important component of the regulatory process necessary to develop Texas LNG's project on its 110 plus acre site with deepwater frontage to the Port of Brownsville shipping channel in Brownsville, Texas, USA.