SK E&C Awarded Contract for Magnolia LNG

December 1, 2014

 

Liquefied Natural Gas Limited informs that its wholly owned subsidiary, Magnolia LNG LLC (MLNG) has agreed to an EPC contract with SK E&C USA (EPC Contract) in relation to the Company’s Magnolia LNG Project. 

The Contract covers the initial 4 mtpa LNG installation, comprising two LNG trains, each with a LNG design capacity of 2 mtpa, two 160,000m3 storage tanks, a jetty and ship loading facility and related infrastructure, and all required approvals and licenses for the full 8 mtpa project. An additional two x 2 mtpa trains (Trains 3 & 4) are planned to follow the initial 4 mtpa installation.

The EPC Contract, which is a Lump Sum Turn Key model, has now been forwarded to BNP Paribas, MLNG’s project finance adviser, Merlin Advisors LLC, the lenders’ technical consultant, and legal advisors White and Case for final review.  The finance adviser review aims to ensure third party acceptability of all proposed EPC Contract provisions to enable MLNG financial close consistent with project timelines. 

The EPC Contract has also been forwarded to Stonepeak Partners LLC, the proposed Magnolia LNG Project Equity partner, for their final review together with its advisers.

Execution of the EPC Contract is planned for later this month, subject to LNGL Board approval. The capital cost for the initial contracted work totals $1.986 billion for the two‐train installation and associated facilities, and comprises two components:

1. A Lump Sum, Fixed Price of US$1.391 billion (70% of contract value) valid through 30 June
2015; and

2. A Provisional Sum of US$595 million representing 30% of contract value.

During the period to 31 March 2015, the Company and SK E&C will conduct further optimisation and cost reductions. Any resultant cost reductions will be apportioned between the parties, but in any event, the Lump Sum component will not exceed the agreed fixed price of US$1.391 billion. The Company and SK E&C will continue to develop, finalise and agree the Provisional Sum by 31 March 2015, with the agreed amount converting to a lump sum, fixed price contract at that time, also valid to 30 June 2015. 

During the period to 31 March 2015, the parties will also agree to the capital cost for Trains 3 & 4, currently estimated at ~US$1 billion total for the two trains, and a timeline to fully implement the 8 mtpa MLNG Project at an estimated total cost of US$3.5 billion.
 